Key points
- The new contracts are worth about AED 56.5 billion.
- Total contracts and packages awarded for the project now stand at about AED 80 billion.
- About 14,000 workers are currently on site, with more than 21.3 million working hours logged.
Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, Deputy Prime Minister, Minister of Defence and Chairman of The Executive Council of Dubai, announced on 26 November 2026 the award of a further series of contracts for Al Maktoum International Airport, with a combined value of about AED 56.5 billion. The announcement was reported by the Emirates News Agency (WAM).
What the contracts cover
The packages are for Phase One of the airport and include:
- substructure and infrastructure works for the West Terminal Building, Concourse 1 and Concourse 4, including basements, tunnels, ramps, short-term car parks, the Ground Transportation Centre and metro interface works;
- superstructure, roofing, facades, fit-out and building systems for Concourses 2 and 3;
- a major power package with two principal 132/11 kV substations and related cabling.
In the preceding phase, Dubai Aviation Engineering Projects awarded about AED 23.815 billion of contracts for enabling works, substructure packages, the Automated People Mover and the Baggage Handling System.
Progress on site
According to Dubai Aviation Engineering Projects, enabling works in the Concourse 2 and 3 zones and the central area of the site are nearing completion. Figures released with the announcement include:
- more than 24.23 million cubic metres excavated and 5.2 million cubic metres backfilled;
- 7,635 piles completed;
- over 875,603 cubic metres of concrete placed and 226,270 tonnes of reinforcement steel installed for Concourses 2 and 3.
Why it matters
Sheikh Hamdan said the contracts are "a significant step in the development of Dubai's new global aviation hub". Sheikh Ahmed bin Saeed Al Maktoum, Chairman of Dubai Aviation City Corporation and of Dubai Aviation Engineering Projects, said the project has entered a phase of large-scale construction. The airport is linked to the goals of the Dubai Economic Agenda D33, which aims to double the size of Dubai's economy. The announcement did not name the contractors or give a new opening date.